A wind-power-to-hydrogen project that will use hydrogen and carbon dioxide to produce 20,000 tonnes of biomethane annually has received filing approval in Shuangliao, Siping, Jilin Province, according to the Jilin Province Online Investment Project Approval and Supervision Platform.


Project details


Project code: 2610-220382-04-01-343404

Location: Shuangliao, Siping, Jilin Province, China

Total investment: RMB 200 million (approximately US$28 million)

Scheduled construction start: June 2027

Scheduled completion: June 2028


image.png


Project scale and capacity


The project will occupy 20,000 square metres of land and have a total building floor area of 17,000 square metres.


Above-ground facilities, including offices, a control room and a protein production workshop, will cover 3,000 square metres. Underground facilities, including a fire-water reservoir and pump station, will cover 1,000 square metres. The project will also include 3,000 square metres of paved roads and 10,000 square metres of equipment buildings.


The project is designed to produce 20,000 tonnes of biomethane and 4,000 tonnes of biological protein annually. It is expected to consume 11,000 tonnes of hydrogen and 60,000 tonnes of carbon dioxide per year.


Before construction begins, the project must complete the required procedures under national and provincial regulations, including those relating to land-use planning, energy conservation, environmental impact assessment, safety assessment, housing and urban-rural development, water resources and meteorology.


Source: Jilin Province Online Investment Project Approval and Supervision Platform